Select Page

Team Gliders have adopted Scrum a few months back. All team members were new to Agile/Scrum, they attended a two-day workshop to get to speed.

The charter of the team is to provide enhancements to different applications, in a suite of Trading applications. Team members were responsible/owned an application or two and worked in silos. The workload was uneven, it depended on the requests from the users of the different applications. One of the intent of the move was to leverage the team to deliver better and cross-skilling of the team for achieving the same.

Manish an experienced Scrum Master, from outside the team, was picked to play the Scrum Master role. The team started with two-week sprints and completed the first four sprints with Manish as SM. The team liked the move to Scrum, they were happy to get an opportunity to work in different, but related areas. There was bonhomie due to the increased need to collaborate.

At this juncture, Manish moved on as intended, and Neeta a team lead was picked to play the role of Scrum Master. In the seventh sprint, that is the third sprint for which Neeta was the Scrum Master, the team seemed to have lost its steam. There were murmurs that Agile Scrum was taxing and strenuous.

Some probing by Sandeep, the manager of the team revealed that they considered the move to Scrum to be OK. Couple team members feedback was that they were neutral about it, which seemed more of a diplomatic reply.

Sandeep could not see much difference between the way Manish and Neeta were playing the role of the Scrum Master. Sandeep’s inference is that the team was OK with Manish playing the role of SM with no domain knowledge. With Neeta, as the Scrum Master having domain knowledge, they feel uncomfortable, especially if the progress is not as expected.

Sandeep also felt that the team was not used to doing any kind of planning in the past, felt uncomfortable due to the planning and the transparency inherent in Scrum. He had reiterated to the team that the Sprint backlog is to be committed, based on what the team thinks it can achieve. The team was able to complete 70-80% of the stories.

He approaches you, an Agile Coach and seeks your intervention in resolving the issue. What would your approach be?

Suggested Solution:

At the outset, it was fairly clear that planning was the cause of the discomfort. It was also evident that the team appreciated many of the positives from the Agile adoption.

A survey was done to get inputs from the team members on which Principle of agile was most practiced/relevant and which was least practiced/relevant. This made team members review the Principles and appreciate the same. The same was presented to the team and after a healthy discussion a common understanding evolved.

A quick review of the retrospectives was done in parallel, it showed that (1) being able to learn related area or cross-skilling and (2) collaboration between team were the clear positives. On the flip side (1) Estimation and (2) being unable to meet the forecast were the areas that needed improvement.

A few of the team were met 1-on-1 to understand any issues that may not have surfaced.

In the discussions one very surprising fact emerged, that the team was giving aggressive estimates to look good, though there was no need to do so.  Once this emerged, we walked through the team on “whys” behind the planning – understand the work, break it down and make a forecast. In addition, it was reiterated that on can go wrong with the estimate, but one needs to learn from that and try to better it, set the team on the right track.